The Marigold Road improvement project will begin the week of November 27, 2017. The scope of the project includes the complete reconstruction of Marigold Road between Woodridge and Lake Overlook.
Work will be performed between the hours of 7:00 AM and 9:00 PM Monday through Friday.
The first phase of the project will focus on the replacement of sanitary sewer service lines. The roadway will be reconstructed one half at a time upon completion of the sewer work. Roadways within the work area will be limited to local traffic only, with complete road closure at the point where daily sewer construction occurs.
One-way northbound traffic will be maintained during the roadway reconstruction portion of the project. Southbound traffic will be detoured via adjacent local streets.
Please use caution when driving through this area.
Completion of the project is scheduled for late-summer 2018.